Friday 21st July 2010

The rate of work has increased again this week. Several of the timber frame side panels have been positioned at the rear and Western sides of the building.
The concrete floors for the toilets, boiler room and store were laid late today.
Most of the scaffolding is now in place.
Once again we have had a week of substantially fine weather. Most of the site is covered by the building's roof. There was one day of heavy rain.